| Date |
Event |
| 2006-02-01 |
Beginning of ASR Run |
| 2006-02-12 |
End of ASR Run - output sent back to ELDA - word graphs available to SLT |
| 2006-02-15 |
Preliminary ASR results sent to participants + reference transcriptions |
| 2006-02-24 |
Final ASR results sent to participants |
| 2006-02-15 |
Beginning of SLT Run |
| 2006-03-01 |
End of SLT Run - output sent back to ELDA |
| 2006-03-05 |
Preliminary SLT automatic results sent to participants |
| 2006-03-15 |
Final SLT results sent to participants |
| 2006-02-24 |
Beginning of TTS Run - Voice conversion evaluation |
| 2006-02-27 |
Beginning of TTS Run - Prosody module, Acoustic module, Expressive Speech, TTS component evaluations |
| 2006-03-01 |
Beginning of TTS Run - Text processing module evaluation |
| 2006-03-02,03 |
End of TTS Run - Text processing, Prosody, Acoustic, Voice conversion, Expressive Speech, TTS component evaluations - Output sent back to ELDA |
| 2006-03-03 |
Beginning of TTS Run - End-to-End evaluation |
| 2006-03-03,04 |
End of TTS Run -End-to-End evaluation - output sent back to ELDA |
| 2006-03-08 |
ELDA conducts Subjective tests |
| 2006-03-14 |
End of Subjective tests |
| 2006-03-17 |
TTS Results sent to participants- End-to-End evaluation , Prosody, Acoustic, Voice conversion, Expressive Speech, TTS component evaluations |
| 2006-03-31 |
TTS Results sent to participants - Text processing evaluation |
| 2006-06-19,20,21 |
TC-STAR Evaluation Workshop in Barcelona |